Project Status Summary Report
*10-08-0009 Rehab Boiler Meats Lab
Scope of Work: FY 08 DEF MAINT Project- Project initiated Contact Dr. Cawthon or Allen Morgan for further information.
Status:Steve met with new staff at Meats lab.
Completion Schedule Date : 4-30-09
_________________________________________________________
*03-08-0036 Environmental Services New Facility Evaluation
Scope of Work: Project initiated Estimate cost of various modular office buildings with the cost of purchasing and leasing with a minimum of a three year lease.
Status: Bob has cost estimate on modular building. Cost estimate has been developed and forwarded to Mr. Graham. Unable to move forward with this project until buildings on site have been moved. Kent thinks we may need to have asbestos abatement done on the white house - the rock house has already been sold.
Completion Schedule Date : 1-05-09
_________________________________________________________
10-08-0009 Lighting System Replacement Horse Lab
Scope of Work: Project initiated. Install new vapor-proof T8 fluorescent lighting that is pendant-mounted. Replace lighting in the tack rooms, storage rooms, and apartment with compact fluorescent and standard fluorescent lighting. Upgrade class laboratory space and restroom with T8 design.
Status: Gary Raymond is waiting on final drawing and light selection from Steve Bowman.
Completion Schedule Date : 4-30-09
_________________________________________________________
10-07-0006 Rehab Academic Facilities UFICC FY07
Scope of Work:Rehabilitation projects for Academic facilites as identified by the UFICC and approved by the President for FY 2007.
Status: Web site updating for UFICC members.
Completion Schedule Date: 04-30-08
_________________________________________________________
03-07-0033 Rehab Health & PE Building
Scope of Work:Rehab 1455 SF for police, 1815 SF for PE offices, 1667 SF for ROTC.
Status:Two his project: Sports Information office and Police Office Expansion. Will have to remove old AHU unit, install new one in racquetball courts. Stamped drawings and plans will be complete by 11/21/08. final pricing from Alpha due by 11/24/08. If approved, construction will being over Christmas holiday or January 1, 2009.
Completion Schedule Date : 8/23/08
_________________________________________________________
10-08-0006 Install Concrete Sidewalk West Jones & Rome
Scope of Work: Install 6' wide concrete sidewalk and ramps, as required, to promote pedestrian safety leading to and from the new Recreation Center. To include lighting also.
Status:Traffic signs outside Police Station were reinstalled; project is complete. Dr. Mercer wants to go forward with Phase II of project, with sidewalks down Rome Street. Waiting on direction on this additional work.
Completion Schedule Date: 8/30/08
_________________________________________________________
10-08-0008 Rehab Academic Facilities FY 2008
Scope of Work: Rehabilitition of Academic Facilities as identified bythe UFICC Committee and approved by the President.
Status: Approximately 11-12 projects approved and will be distributed for planning purposes within 1-2 weeks.
Completion Schedule Date: 4/30/09
_________________________________________________________
10-08-0009 Deferred Maintenance Rehab FY 2008
Scope of Work: Deferred Maintenance projects as identified by the Facilities Analysis survery and reported on the CB MP2 schedule.
Status:Projects established.
Completion Schedule Date: 4/30/09
_________________________________________________________
08-07-0059 Telecommunication Infrastructure Project
Scope of Work: Up-grade Telecommunication Infrastructure.
Status:The initial project has been completed and we are awaiting Future Com to complete. Aaron spoke with Mike Williams on August 14th. He stated he was waiting for his new cabinet to arrive. Once the cabinet is ready, Future Com will come and install the wireless system in 5 days. The new completion date will be September 30, 2008.
Completion Schedule Date: 9/30/08
_________________________________________________________
12-08-0014 Stenholm Office Mock-up
Scope of Work: Design and build a mock-up of Senator Charles Stenholm's office in the lobby of the Tarleton Center. The area will be surrounded by plexi glass for viewing. The project has President McCabe's approval.
Status: Prtesident Dottavio is reviewing the project to determine if this is the final location. He will also meet with Dr. Robitalle to review her concerns. Waiting on his approval and/or direction.
Completion Schedule Date:6/30/09
_________________________________________________________
10-08-0009 Roof Restoration Central Receiving Warehouse
Scope of Work: Inspect standing seam roof, flashing and gutters. Recaulk and replace damaged screws. Exterior primer and paint. Metal repair related work.
Status: There is a small leak over the warehouse entry door (3'x&'). Merit will be on compus to review over the next three weeks. Beth has asked that the skylights be kept. Alpha will do some further checking for clip-on grills for fall protection.
Completion Schedule Date: 6-15-08
_________________________________________________________
10-08-0009 Rehab Flooring Hydrology
Scope of Work: Replace carpetiing.
Status:Project is complete as originally contracted, although we may issue a change order to remove the tile in Room 115. We need more carpet. Gomez is currently looking for additional carpet with a matching color lot number.The completion date will be September 20, 2008.
Completion Schedule Date: 9-20-08
_________________________________________________________
10-08-0009 Rehab Doors Swine Farrowing
Scope of Work: Please contact Dr. Cawthon or Allen Morgan for further information.
Status: Project is complete except for hardware.
Completion Schedule Date: 4-30-09
_________________________________________________________
01-08-0016 Rehab TSC lower level
Scope of Work: Project to include space for offices for Center for Diversity Initiatives, Copy Center, student study carrels, offices for Student Government.
Status: Plans are delivered and bids are due into Alpha on December 1, 2009.
Completion Schedule Date:
_________________________________________________________
01-08-0019 Rehab Academic Affairs Offices
Scope of Work: Install window in existing door in room 234. Install new door hardware to existing doors in rooms 237 & 238 and install window in wall next to existing door in room 238. Provide and install window blinds for corridor windows. Provide and install fire resistant drapes in rooms 237 & 238.
Status: Aaron sent email to Dr. Chilton asking for direction; do we proceed or close and wait for new Provost to revive?
Completion Schedule Date:
_________________________________________________________
01-08-0020 Replace Exterior Lighting @ Rec Sports
Scope of Work: Remove sub-standard contractor installed exterior lighting and install the Tarleton campus standard exterior lighting at the newly constructed Recreational Sports Building.
Status: Trae Oliver has come up with a factory solution to construct the block out ring. Trae is also looking at the cost to replace the entire head only. This may actually be cheaper due to the high pressure sodium upgrade. The labor savings could be substantial.
Completion Schedule Date:
_________________________________________________________
02-08-0028 Demolition of Old Dining Hall
Scope of Work: Demolition of structures, foundations, and piers down to 2 to 3 feet below grade. Remove and fill basement (based on 4,000 SF). Remove parking areas where applicable. Haul off and dispose of debris in a legal manner. Site left in clean condition. Demolition permits.
Status: The walls sealing the steam tunnel will be completed today. Contractor continues to backfill basement. The steam pipe has been installed, with saw cutting completed on 12/15/08. The roadway is coming out, except for an 8' walkway, to be completed by 12/24/08. Gene cautioned contractor again to be mindful about steam lines and lighting circuits. Will be bringing in select fill to sod, will seed bermuda and rye, so that area can be done at once. A meeting will be held with Gary Raymond, Terry, Aaron and Mike Newton to discuss irigation system. Will have Alpha get
Completion Schedule Date : 12/30/08
_________________________________________________________
02-08-0029 Demolition of Houses 1429 & 1401 Jones
Scope of Work: Demolitionn of structures, foundations, and piers down to 2 to 3 feet below grade. Remove parking areas where applicable. Haul off and dispose of debris in a legal manner. Remove and backfill pool (1429). Site left in a clean condition.
Status: Houses are on hold pending a letter from the historical board. Mr. Graham may contact the historical board for a review.
Completion Schedule Date : 12/30/08
_________________________________________________________
02-08-0030 Demolition of Apartment Complexes Vanderbilt ST.
Scope of Work: Demolition of structures, foundations, and piers down to 2 to 3 feet below grade. Remove and fill basement (based on 4,000 SF). Remove parking areas where applicable. Haul off and dispose of debris in a legal manner. Site left in clean condition. Demolition permits.
Status: Apartment complexes came down as of 10/11/08. all poles were removed except on Embarq pole that will not be in the way. Project is ready to C-30. Aaron has asked Gary Raymond to check on fence leasing dates.
Completion Schedule Date :
_________________________________________________________
02-08-0031 Rehab Admin Annex I
Scope of Work: Rehab existing Print Center area for faculty office space and human Resources expansion. The space renovation of the Admin Annex Building as described below is approved: After the Sports Info personnel have moved to Wisdom Gym, Mr. Stan Swan will be assigned to a
Status:Contractor walk thru was held 11/16/08 with Alpha, Gene, Trae and Marchelle Lee. Drawings will be complete by Friday, 11/21/08.
_________________________________________________________
03-08-0033 Roof Repairs FY 2008
Scope of Work: Repair deteriorated foam roofs on the Physical Plants, Thompson Student Center, Finenn Arts Building and the Health and PE Building.
Status: Joe will make recommendations for the direction of this project.
Completion Schedule Date :
_________________________________________________________
03-08-0034 Construct Advising Center TSC Lower Level
Scope of Work: Construct Advising Center in the lower level of the Thompson Student Center.
Status:This project is complete. Ready to C-30.
Completion Schedule Date : 9/30/08
_________________________________________________________
03-08-0037 Rehab Meats Lab Flooring and Hot Water Heater
Scope of Work: Replace water heating system at the Meats Lab.
Status: Steve is meeting with Kevin Alford this morning to review the current requirements. Due to client needs, this project will be expedited. Joe will stamp off on drawings. Gary Raymond will meet with Kevin as the project develops.
Completion Schedule Date :
_________________________________________________________
10-08-0008 Construct Equipment Enclosure (Library)
Scope of Work: Construct a CMU tile with brick facade enclosure around the existing equipment.
Status:Concrete pad poured bulged in front. The area was removed and will be re-poured this week. Brick work to start 11/24/08. We will prepare an in-house change order and memo documenting why project is delayed.
Completion Schedule Date : 4/30/09
_________________________________________________________
10-08-0008 Expand Sports Medicine Facility
Scope of Work: Increase size of current facility.
Status:This is becoming a much larger project. Mr. Graham may pull this project in order to develop a Master Plaln for this area. We continue to develop plans for construction estimate, and are nearing completion of concept drawings. Mr. Dixon raised the question of the bathrooms by the classroom in this area; Joe asked him to submit a project request form.
Completion Schedule Date : 4/30/09
____________________________________________________________________________
10-08-0008 Rehab Doors Rm 107 & 119 Fine Arts Complex
Scope of Work: Replace double wood doors on front and back of choir rehearsal room 107 and 119.
Status:Alpha will be installing eight sets of acoustical double doors. Gary Raymond is waiting on shipping date for doors.
Completion Schedule Date : 4/30/09
_________________________________________________________
10-08-0008 Rehab Stage Floors @ Fine Arts
Scope of Work: Repair, screen and refinish stage floors.
Status:Prestige will be coming in during the Christmas days to work. Joe asked Aaron to ask the contractor's opinion as to how many more sandings can be done for these floors, Mr. Dixon wondered about protection from sanding debris, and was told that contractor's sanders have a HEPA bag that collects dust. Start date 12/15/08
Completion Schedule Date : 4/30/09
_________________________________________________________
10-08-0008 Rehab Gutter System @ Equine Center
Scope of Work: Repair/replace downspouts on gutter system on Equine Center Arena. Install gutter.
Status:Alpha should have a proposal ready to repair and replace gutter system.
Completion Schedule Date : 4/30/09
_________________________________________________________
10-08-0008 Rehab Room 130A Hydrology Engineering
Scope of Work: Construct a wall to split HYEG 130A (Fluids Lab) into two self-confined areas.
Status:The roolup door has arrived, and work will be scheduled soon.
Completion Schedule Date : 4/30/09
_________________________________________________________
10-08-0008 Install Wall Talker in Hydrology Classrooms
Scope of Work: Installation of Wall talker surfaces in each of the 4 HYEG classrooms.
Status:The three 4' x 8' whiteboards have been installed. Once all labor is in, project can be closed. Larry will meet with client prior to sending out a project survey form.
Completion Schedule Date : 4/30/09
_________________________________________________________
05-08-0043 Ag Center Storm Damage Rehab
Scope of Work: Construct new metal covers over open animal pens to repair/replace existing which was storm damaged.
Status:TAllan Morgan is designing his own center pens. Fred Parker will set up a meeting with client to review drawing. Larry Smith will do elevation shots next week. Finished design and drawing will be ready by 12/15/08.
Completion Schedule Date : 4/30/09
_________________________________________________________
10-08-0008 Rehab Window Covering Teaching Pavilion
Scope of Work: Remove old blinds and replace with new white blinds.
Status:The blinds arrived last Thursday; four were the wrong color and three were the wrong size. Alpha will work through Danny's to get the order correct, but do not have a definitive date at this time.
Completion Schedule Date : 4/30/09
_________________________________________________________
10-08-0008 TSC Floor Stabilization
Scope of Work: Reinforce the large red tiles on the terrace to stabilize flooring
Status:This project is complete and we are reviewing progress for approximately 30 days to allow for student traffic before closing enuring that no additional work is needed.
Completion Schedule Date : 4/30/09
_________________________________________________________
05-07-0043 Library Emergency Generator Replacement
Scope of Work: Replace 25 yr old generator and transfer switch with new generator and transfer switch. Needed for new loads in facility for HVAC for telecom switch room, emergency lighting, elevators, sump pumps and card access system.
Status: Project was completed 11/14/08. Will forward project survey form to Terry to send to client.
_________________________________________________________
01-08-0017 Rehab Humanities Elevator
Scope of Work: Installation of new submersible power unit to replace existing power unit, remove existing door operator and replace with linkages, provide new hoist way doors for all entrances with baked enamel painted finish; provide new interlocks, closers, hanger, tracks rollers, and door gibs.
Status: Work is going on, have till the 22nd to finish. Contractor should be able to finish without a problem.
Completion Schedule Date:8-22-08
_________________________________________________________
03-08-0032 Install Security Cameras @ Ag Center
Scope of Work: Provide labor, cable, power supply and miscellaneous materials to install two high resolution digital day night PTZ Video Surveillance cameras at the Agricultural Farm & Recycle Plant.
Status: Complete except for warranty information.
Completion Schedule Date : 6/15/08
_________________________________________________________
08-06-0056 POR - Central Plant Loop Expansion
Scope of Work:Program of Requirements - For the expansion of the existing Central Plant Loop.
Status: 90% review meeting was held on Monday - presented list of concerns. Money is looking good, should be able to get options.
Completion Schedule Date:
_________________________________________________________
09-07-0001 Campus Lighting Retrofit
Scope of Work: Retrofit lighting in E & G areas campus wide.
Status: Project had been on hold, was recently reactivated.
Completion Schedule Date: 8-31-08
_________________________________________________________
10-07-0006 Rehab AG Room 103
Scope of Work: Repair mold damage in Room AG 103, paint, replace window treatments and chairs.
Status: Donna is tryiing to get a delivery date for the HON chairs chosen. Company is way behind due to the number of orders submitted before HON raised prices.
Completion Schedule Date: 4-30-08
_________________________________________________________
08-07-0057 Chair Rehab Business Bldg.
Scope of Work: Replace chairs in room #187. Business Administration Building. Replace swing out shairs with replacement chairs. Use swing out chairs removed from room 187 for spare parts on rest of building. The new chairs cannot match the old chairs in color.
Status: Furniture is due to be delivered on 9/24/08. Tables and chairs in two classrooms were completely replaced, with swing arms removed from chairs in another classroom.
Completion Schedule Date: 3-01-08
__________________________________________________________
05-08-0044 Rehab Gym Floors in Health & PE Facilities
Scope of Work: Install NCAA required 3 point line in Main Gym and adjust graphics throughout. Replace chipped wood for floor use, remove side
Status: The floors should be complete.
Completion Schedule Date:
_________________________________________________________
05-08-0045 Resurface Tennis Courts
Scope of Work: Resurface four existing tennis courts, install new tennis nets, center anchors and tie downs and replace deteriorated wenches on nets.
Status: The new courts are complete and a project survey has been sent out to the client. Met with Coach Drake last week and he is very satisfied with the outcome of the colors and surface quality.
Completion Schedule Date:
_________________________________________________________
06-08-0046 Rehab Athletic Irrigation Storage Tank
Scope of Work: Determine cost and feasibility to either replace tank or install bladder.
Status: Alpha proposal to replace tanks was received 11/16/08. Will prepare a draft C-1 for funding to send to Mr. Graham. Terry will prepare cost to detach plumbing and get cost to replace pump on Tank 1. Several staff have suggested using the same make and model of VFD pump as on Tank 2, as it has performed well. Terry will also have a PM work order set up to do monthly test of the tank water.
Completion Schedule Date:
_________________________________________________________
07-08-0047 Update TAMUS Design Guide for Tarleton
Scope of Work: Project Initiated Update TAMUS Design Guide for Tarleton.
Status: Aaron is wrapping up work on these guidelines for roofs, doors, openers, locks, etc. If anyone has anything to be included, please forward to Aaron quickly.
Completion Schedule Date:
_________________________________________________________
07-08-0048 Rehab Room 208 Tarleton Center
Scope of Work: Project Initiated Develop POR and initial cost estimate to rehab room 208 in the Tarleton Center to provide more room for
Status:This project is onhold until the Admin Annex II project is approved.
Kent has done asbestos inspection, and Fred Parker's engineer ash inspected basement floor Need toidentify where steam line runs under floor in basement.
Completion Schedule Date:
_________________________________________________________
07-08-0050 Rehab Admin Annex II - Phase II
Scope of Work: Develop preliminary drawings and cost estimate to develop office space to accommodate
Status:Project is under review for approval. Cost will determine direction, and have an impact on CAE project. Hulsey Engineering to be complete with plans Friday, 11/21/08. Aaron has asked Trae to check if these could be received a day early for additional review time.
Completion Schedule Date :
_________________________________________________________
08-08-0051 Rehab Room 205 O A Grant
Scope of Work: Rehab Rm 205 from a classroom to a computer lab to include providing power down the hallway.
Status:The design is nearing completion along with the cost. Joe has asked that chases be constructed to allow for a safer electrical run and aesthetically acceptable look.
Completion Schedule Date :
_________________________________________________________
08-08-0052 Rehab Parking @ Equine Center
Scope of Work: Rehab handicap parking and ramps to meet ADA guidelines at the Equine Center.
Status:Larry will have pricing by Friday 11/21/08.
Completion Schedule Date : 9/13.08
_________________________________________________________
08-08-0053 Install Fall Protection System @ Stadium
Scope of Work: Install a fall protection system on top of the Press Box to provide applicable protection to individuals.
Status:Have received documents from Fred parker, jst need waraanty information. Gary Raymond will check on it.
Completion Schedule Date : 10/30/08
_________________________________________________________
08-08-0054 Replace Asbestos Floor Tiles in Wisdom Gym
Scope of Work: Replace floor tiles in Wisdom Gym containing asbestos.
Status:Aaron met with Kent,it will cost about $50,000 to abate asbestos and install new floor tiles. Project may be done in future, possibly next summer or Christmas 2009, will be closed out for now.
Completion Schedule Date :
_________________________________________________________
08-08-0055 Construct Dumpster Area @ New Dining Hall
Scope of Work: Construct a concrete pad and fence at the New Dining Hall on the east end to be located between Venture and Central Plant.
Status:Larry has completed estimate, needs approval to build. Aaron will send a memo to Dean jergins, with a copy to Joe, requesting approval to proceed.
Completion Schedule Date :
_________________________________________________________
WO # 35635 Install Window for Student Life
Scope of Work: Remove drywall and install one 4' x 6' metal framed window. Repaint wall.
Status:Projecy is complete.
Completion Schedule Date :
_________________________________________________________
09-09-002 Turfgrass Expansion
Scope of Work: Provide electrical needs in the garage, large storage room and small storage room.Provide potable water.
Status:Hennen Cummings has sent in a request for this work as an UFICC project. Current project will be closed.
Completion Schedule Date :
_________________________________________________________
09-09-01 Install ADA Door Opener @ Rec Sports
Scope of Work: Install 2 ADA door openers w/ remote push buttons on Rec sports Building.
Status:Work completed by Maintenance.
Completion Schedule Date :
_________________________________________________________
10-09-003 Sponsorship Wall @ Library
Scope of Work:Develop programmatic sketches and budget estimate for the construction of a sponsorship wall similar to that in the Health and PE Complex.
Status:Design and estimate are complete, and have been sent to Donna Savage for fund raising. Project will be closed until client has funding.
Completion Schedule Date :
_________________________________________________________
10-09-004 Rehab Basement Doors @ Hunewell Annex
Scope of Work:Remove old basement door jamb and weld in a new one.
Status:Work has been completed Gary Stout provided account number for WO, and a project survery form will be forwarded.
Completion Schedule Date :
_________________________________________________________
10-08-0009 O A Grant Revitalization
Scope of Work:Project will include the rehabilitation of flooring, painting the facility and replacement of certain classroom furnishings.
Status:This project is on a tight schedule, and must be complet by the start of classes on January 12, 2009 Paint on first floor and second floor hallways is complete. Carpet is on schedule, furniture arriving 1/9/09, to be assembled by KI. There are asbestos issues in two rooms. Karl Easterling will be moving AV equipment out of five rooms as soon as finals are over. The date lines in these rooms will be move to the oposite wlll, and ther may be some electrical needs. Additional smart boards are being installed in these rooms.
Completion Schedule Date : 1/12/2009
_________________________________________________________
109-09-006 Rehab Academic Facilities FY 2009
Scope of Work:Rehabilitation projects for Academic facilities as identifiied by the UFICC.
Status:
Completion Schedule Date :
_________________________________________________________
07-08-0049 Rehab Presidential Offices
Scope of Work:Create nenw design concepts/ ideas for the President's offices, including furniture.
Status:Interior designer presented color board to President Dottavio.
Completion Schedule Date :
_________________________________________________________
11-09-0008 Install Volleyball Courts @ Rec Sports
Scope of Work:Install 2 volleyball courts on NE corner of Rec Sports
Status:Working on two price estimates; on done through Alpha and one done in-house. A meeting will be set up with Gary Raymond, Aaron, Larry, Robert Nimmo, and Gene the week after next to discuss need.
Completion Schedule Date :
_________________________________________________________
11-09-0009 Construct Athletics Storage Building
Scope of Work:Provide labor to assemble a donated metal building at North Concession Stand.
Status:This project will need to capitalized. Joe has also requested that we prepare a zero dollar contract for this work, detailing what is to be done, and the value of the donated bulding and concrete work.
Completion Schedule Date :
_________________________________________________________
08-08-0056 POR- Central Plant Loop Expansion
Scope of Work: Program of Requirements:For the expansion of the existing Central Plant Loop.
Status:Steve is working with System. Project has been delayed for two months. Expect to lower bids in February.
Completion Schedule Date:
_________________________________________________________
08-08-0056 Re-lamp Memorial Stadium
Scope of Work: Contact Dr. Cawthon or Allan Morgan for further information.
Status:x
Completion Schedule Date :
_________________________________________________________
08-08-0057 Connect Bender/Ferguson Hall to Central Loop
Scope of Work: Connect Bender/Ferguson halls to the Central Loop which will include connection four.
Status:Proposal is on Dr. Mercer's desk, waiting for her signature.
Completion Schedule Date :
_________________________________________________________
08-08-0058 Door Replacement @ Schaffer Building
Scope of Work: Replacement of doors and locks at the R C Schaffer building in Ft. Worth. Transfer existing card system.
Status:Project initiate.
Completion Schedule Date :
_________________________________________________________
01-04-0025 New Dining Hall
Scope of Work: Funds for the program of requirements and related project costs System Project.
Status: The controls are still not working properly, though the costs have come down slightly.
Completion Schedule Date:
_________________________________________________________
02-04-0028 Recreational Sports Facility
Scope of Work: Appropriate funds for the program of requirements and associated project costs.
Status: There are still a few punch list items remaining. Based on feedback from the System, we have accepted the building, and will have to deal with the remaining problems. this project will be closed.
Completion Schedule Date: 9/27/07
_________________________________________________________
11-05-0023 Develop Master Plan 2020
Scope of Work: Develop Master Plan for Tarleton State University program of requirements for A&M University system.
Status:There will be a presentation in December to the President's Council, to finalize what Freese 7 Nichold feels needs to be done. Expect to finish in Spring.
Completion Schedule Date:
_________________________________________________________
12-07-0022 Construct New Nursing Building
Scope of Work: Construct new 100,000 SF Nursing Building on Tarleton State University campus TRB project.
Status:This project will be done with a construction manager at risk, with Byrnes as the contractor. We have gone through the preliminary designs.
Completion Schedule Date: 9/01/10
_________________________________________________________
02-07-0026 Dairy Center
Scope of Work: Construct new Dairy Barn - Includes freestall barn of 65,000 GSF milking parlor, holding pens & office space.
Status: A telephone conference meeting will be held on Friday to discuss project. Working on permitting, need to determine where pwere is coming from.
Completion Schedule Date: 9/01/10
_________________________________________________________
07-01-0041 Boiler UST Closure
Scope of Work:Phase I- Fuel removal and tank cleaning. Phase II- Soil sample collection Phase III- tank closing
Status:Funding has been transferred. In February, TCEQ will revise regulations once again, this time reverting to old rules. Waiting on recommendations from project manager at TCEQ.
Completion Schedule Date :
_________________________________________________________
10-09-0005 Install Camera System @ Library
Scope of Work: Installation of one DVR system and eight single lens cameras and one dual lens camera in locations.
Status:Alpha completion 1/17/09.
Completion Schedule Date:
_________________________________________________________
_______________________________________________________