Timeline
| Planning Component | Expanded Activity Description | Leadership | Activity Period |
|---|---|---|---|
| Vision and Mission Statement | Review current strategic planning materials Deliverable: Document providing vision and mission statement |
Executive Cabinet | March 2012 |
| Stakeholder Engagement Plan | Council will develop comprehensive plan to engage stakeholders and to collect rich, manageable data Deliverable: Engagement plan submitted to cabinet for approval |
Planning Council | February ‐ March 2012 |
| Environmental Scan | Collection of various data to form a snapshot of our current state, to include:
|
Planning Council | January ‐ June 2012 |
| Dissemination/Information | Dissemination of summary findings document to stakeholders, including:
|
Planning Council | July‐September 2012 |
| Stakeholder feedback | Campus and virtual forums providing stakeholders opportunity to provide input in identifying strategic issues for consideration in strategic planning. Provide campus administrative entities with strategic plan template (electronic) and invite submission of unit/division strategic plans. Deliverable: Stakeholder Data Summary
|
Planning Council | October 2012 |
| Strategic Imperatives/Goals/Objectives | Planning Council will act upon subsequent direction from Executive Cabinet and consultation from UEEC to draft a set of strategic imperatives/goals/objectives. Deliverable: Planning Council recommendations submitted to Executive Cabinet. |
Planning Council | November 2012 |
| Strategic Programming – Feedback |
Planning Council will utilize campus and virtual forums to disseminate strategic imperatives/goals/objectives and solicit input from stakeholders on strategies. Deliverable: Report from Planning Council to Executive Cabinet summarizing
|
Planning Council | December 2012 |
| Strategic Programming – Formalization |
Planning Council will consider stakeholder feedback, direction from Executive Cabinet and consultation with UEEC in developing strategies for inclusion in strategic plan. Deliverable: Recommendation from Planning Council to Executive Cabinet identifying key strategies. |
Planning Council | January‐February 2012 |
| Evaluation plan | UEEC and AAC will develop evaluation plan that includes, among other components, key performance indicators and a process for identification and evaluation of emergent strategies. Deliverable: Evaluation plan submitted to Executive Cabinet for approval. |
UEEC and AAC | March – April 2013 |
| Submission/Project Completion | May 2013 |